Question: 1. Consider a project having the following seven activities: Optimistic Most likely Pessimistic Immediate Time (o) Time (m) Time (p) Activity Predecessors (weeks) (weeks) (weeks)
1. Consider a project having the following seven activities:
Optimistic Most likely Pessimistic
Immediate Time (o) Time (m) Time (p)
Activity Predecessors (weeks) (weeks) (weeks)
A none 4 7 9
B none 3 5 8
C A 2 4 6
D A, B 6 9 9
E C, D 5 5 5
F B 2 5 9
G E, F 3 3 6
(a) What is the expected time for each activity?
(b) What is the expected project completion time?
(c) What is the critical path?
(d) What are the expected time and variance of each path?
(e) What is the probability that the project will be completed in less than 22 weeks?