Question: 1. Consider a project having the following seven activities: Optimistic Most likely Pessimistic Immediate Time (o) Time (m) Time (p) Activity Predecessors (weeks) (weeks) (weeks)

1. Consider a project having the following seven activities:

Optimistic Most likely Pessimistic

Immediate Time (o) Time (m) Time (p)

Activity Predecessors (weeks) (weeks) (weeks)

A none 4 7 9

B none 3 5 8

C A 2 4 6

D A, B 6 9 9

E C, D 5 5 5

F B 2 5 9

G E, F 3 3 6

(a) What is the expected time for each activity?

(b) What is the expected project completion time?

(c) What is the critical path?

(d) What are the expected time and variance of each path?

(e) What is the probability that the project will be completed in less than 22 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!