Question: Consider a project involving 4 activities, as shown in the following figure. x indicates the current time, and the shaded area indicates the

Consider a project involving 4 activities, as shown in the following figure. "x"
indicates the current time, and the shaded area indicates the percentage that has
been completed. The total planned costs of these activities are (in $000's): A: 100,
B: 110,C:120,D:150.
At time "x", the project actual cost is 250(in $000's).
a) Calculate the project CV, SV, CPI, SPI values at time "X". Is the project within
budget and schedule?
b) Calculate the Estimate at Completion (EAC) if the project continues under the
same condition experienced to date.
c) Calculate the To-complete performance index (TCPI) values based on BAC and
EAC. Explain the meaning of the obtained TCPI.
 Consider a project involving 4 activities, as shown in the following

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!