Question: Consider a project involving 4 activities, as shown in the following figure. x indicates the current time, and the shaded area indicates the
Consider a project involving activities, as shown in the following figure.
indicates the current time, and the shaded area indicates the percentage that has
been completed. The total planned costs of these activities are in $s: A:
B: ::
At time the project actual cost is in $s
a Calculate the project CV SV CPI, SPI values at time X Is the project within
budget and schedule?
b Calculate the Estimate at Completion EAC if the project continues under the
same condition experienced to date.
c Calculate the Tocomplete performance index TCPI values based on BAC and
EAC. Explain the meaning of the obtained TCPI.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
