Question: Consider a project whose activities are listed in the table below. What is the expected duration of the project? Activity Immediate Predecessors Duration (days) A
Consider a project whose activities are listed in the table below. What is the expected duration of the project?
| Activity | Immediate Predecessors | Duration (days) |
| A | None | 5 |
| B | A | 6 |
| C | A | 4 |
| D | B, C | 3 |
| E | D | 3 |
| F | E | 4 |
| G | D | 5 |
| a. | 17 days | |
| b. | 18 days | |
| c. | 19 days | |
| d. | 20 days | |
| e. | 21 days |