Question: Consider a project whose activities are listed in the table below. What is the expected duration of the project? Activity Immediate Predecessors Duration (days) A

Consider a project whose activities are listed in the table below. What is the expected duration of the project?

Activity

Immediate Predecessors

Duration (days)

A

None

5

B

A

6

C

A

4

D

B, C

3

E

D

3

F

E

4

G

D

5

a.

17 days

b.

18 days

c.

19 days

d.

20 days

e.

21 days