Question: QUESTIUN 6 Consider a project whose activities are listed in the table below. Activity F will have slack time as long as... Activity Immediate Predecessors

QUESTIUN 6 Consider a project whose activities

QUESTIUN 6 Consider a project whose activities are listed in the table below. Activity F will have slack time as long as... Activity Immediate Predecessors None None A,B c F LG E a. Duration of F= Duration of G OC. Duration of D + Duration of F > Duration of E+ Duration of G d. Duration of D + Duration of F