Question: Consider a project with 7 activities. The duration, predecessors, and the required number of milling machines for each activity are given in the following table.

Consider a project with 7 activities. The

Consider a project with 7 activities. The duration, predecessors, and the required number of milling machines for each activity are given in the following table. The organization has only 6 milling machines available with them. On which days the resource conflict occurs? What is your suggestion