Question: Consider a project with the activities durations and precedence relations depicted in the table below Activity Immediate Predecessor Duration, weeks A - 3 B A

Consider a project with the activities durations and precedence relations depicted in the table below
Activity Immediate Predecessor Duration, weeks
A -3
B A 4
C A 2
D B, C 6
E C 5
F C 3
G E 7
H E, F 5
I D, G, H 8
Find the early start time (EST), early completion time (ECT), late completion time (LCT), early completion time (ECT) and slack of each activity. Plug only the resulting numbers into the following table. Pay attention to the column names!