Question: Consider a project with the activities durations and precedence relations depicted in the table below Activity Immediate Predecessor Duration, weeks A - 3 B A
Consider a project with the activities durations and precedence relations depicted in the table below
Activity Immediate Predecessor Duration, weeks
A
B A
C A
D B C
E C
F C
G E
H E F
I D G H
Find the early start time EST early completion time ECT late completion time LCT early completion time ECT and slack of each activity. Plug only the resulting numbers into the following table. Pay attention to the column names!