Question: Consider a project with the following activity list. With one day delay in the start of activity B, the duration of the project will be
Consider a project with the following activity list. With one day delay in the start of activity B, the duration of the project will be _____.
Activity Predecessor Duration A - 5 B A 7 C A 3 D C 5 E A 4 F E 4 G B,D,F 2 H G 5
Group of answer choices
21
18
19
20