Question: Consider a project with the following activity list. With one day delay in the start of activity C, the duration of the project will be

Consider a project with the following activity list. With one day delay in the start of activity C, the duration of the project will be _____.

Activity Predecessor Duration (days) A - 2 B A 3 C A 2 D A, B, C 3 E D 4 Group of answer choices

13

11

12

10