Question: Consider a project with the following data. Activity Duration (weeks) Precedence Relationship 1 5 - 2 3 - 3 4 1 4 2 2 5
Consider a project with the following data.
Activity Duration (weeks) Precedence Relationship
1 5 -
2 3 -
3 4 1
4 2 2
5 12 3,4
6 10 5
7 4 5
8 9 6
9 6 7
10 5 7
11 8 9,10
12. The following are the end activities for the project.
| a. | 1
| |
| b. | 2
| |
| c. | 8
| |
| d. | 11
| |
| e. | Both 8 and 11
|
13.
The minimum number of weeks required to complete the project is ...
| a. | 39
| |
| b. | 40
| |
| c. | 41
| |
| d. | 42
| |
| e. | None of the above
|
14.In the project network for the given project definition, the number of arrows that point away from activity 8 is ...
| a. | 0
| |
| b. | 1
| |
| c. | 2
| |
| d. | 3
| |
| e. | None of the above
|
15.The following activity has the maximum slack.
| a. | 10
| |
| b. | 11
| |
| c. | 4
| |
| d. | 8
| |
| e. | 7
|
16.The activity that has the maximum slack has a slack of.
| a. | 1
| |
| b. | 2
| |
| c. | 3
| |
| d. | 4
| |
| e. | 5
|
17.The critical activities in the project are
| a. | 1, 2, 5, 7, 8, 9, 11
| |
| b. | 1, 3, 5, 6, 8
| |
| c. | 2, 4, 12, 4, 9, 11
| |
| d. | 2, 4, 5, 6, 8
| |
| e. | 1, 3, 5, 7, 9, 11
|
18 Activity 7 must be completed by this time to finish the project by the earliest completion time.
| a. | 22
| |
| b. | 23
| |
| c. | 24
| |
| d. | 25
| |
| e. | 26
|
19 Suppose the duration of activity 4 increases to 4 (from 2), the earliest completion time for the project will increase by
| a. | 2 weeks
| |
| b. | 1 weeks
| |
| c. | 0 weeks
| |
| d. | 3 weeks
| |
| e. | None of the above
|
20 Suppose that you are creating a plan to finish the project in earliest completion time. Is the following statement true or false?
Activity 8 must start before Activity 11.
True
False
21 The latest completion time for Activity 8 and 11 should be identical.
True
False