Question: Consider a project with the following information. Activity Duration (days) Predecessor ES EF LS LF Slack 2 3 2 5 0 0 A B D

Consider a project with the following

Consider a project with the following information. Activity Duration (days) Predecessor ES EF LS LF Slack 2 3 2 5 0 0 A B D E A B 0 2 5 2 11 6 5 3 Resource Hours Needed 6 6 5 3 7 2 5 11 7 14 0 2 5 6 11 A C D 11 11 14 0 4 0 Assume that the maximum resource hours per day available for the project are eight. Please identify which day(s) need the most resource hours on the resource loading table