Question: Consider a project with the following information. Construct an AON diagram and use the two-pass process algorithm to find ES, EF, LS and LF for
Consider a project with the following information. Construct an AON diagram and use the two-pass process algorithm to find ES, EF, LS and LF for each activity.
| Activity | Immediate Predecessor | Activity Time (weeks) |
| A | - | 3 |
| B | A | 5 |
| C | A | 7 |
| D | B, C | 3 |
| E | B | 6 |
| F | D,E | 4 |
| G | C | 2 |
8. Enter ES and LF of the following activities:
ES of activity D is :=____
ES of activity F is :=____
LF of activity G is :=____
LF of activity C is :=_____
9. Enter the slack of the following activities:
The slack time for activity G is :=___
The slack time for activity E is :=___
10. The project length is :=____
11. What is (are) the critical path(s)?
Enter 1, if your answer is A-B-E-F
Enter 2, if your answer is A-B-D-F
Enter 3, if your answer is A-C-D-F
Enter 4, if your answer is A-B-D-F and A-C-G
Enter 5, if your answer is A-B-E-F and A-C-G
Answer := ____