Question: Consider a project with the following information. Construct an AON diagram and use the two-pass process algorithm to find ES, EF, LS and LF for

Consider a project with the following information. Construct an AON diagram and use the two-pass process algorithm to find ES, EF, LS and LF for each activity.

Activity

Immediate Predecessor

Activity Time

(weeks)

A

-

3

B

A

5

C

A

4

D

B, C

7

E

B

3

F

D,E

4

G

C

2

ES of activity D is :=

ES of activity F is :=

LF of activity G is :=

LF of activity C is :=

The slack time for activity G is :=

The slack time for activity E is :=

The project length is :=

What is (are) the critical path(s)?

Enter 1, if your answer is A-B-E-F

Enter 2, if your answer is A-B-D-F

Enter 3, if your answer is A-C-D-F

Enter 4, if your answer is A-B-D-F and A-C-G

Enter 5, if your answer is A-B-E-F and A-C-G

Answer :=

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!