Question: Consider a project with the following task information. Activity Immediate Predecessor(s) Activity Time in weeks A None 1 B A 2 C A 3 D
Consider a project with the following task information.
| Activity | Immediate Predecessor(s) | Activity Time in weeks |
| A | None | 1 |
| B | A | 2 |
| C | A | 3 |
| D | A, B | 4 |
| E | C, D | 3 |
| F | D, E | 2 |
If activity C is delayed by three weeks, the revised earliest project completion time is:
Group of answer choices
11 weeks
12 weeks
13 weeks
10 weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts