Question: Consider a project with the following task information. Activity Immediate Predecessor(s) Activity Time in weeks A None 1 B A 2 C A 3 D

Consider a project with the following task information.

Activity

Immediate Predecessor(s)

Activity Time

in weeks

A

None

1

B

A

2

C

A

3

D

A, B

4

E

C, D

3

F

D, E

2

If activity C is delayed by three weeks, the revised earliest project completion time is:

Group of answer choices

11 weeks

12 weeks

13 weeks

10 weeks