Question: Consider a project having the following six activities: (Activity --> Immediate Predecessors --> Time(Weeks) --> Max Crash* -- > Crash cost p/week) A None 6
Consider a project having the following six activities:
(Activity --> Immediate Predecessors --> Time(Weeks) --> Max Crash* -- > Crash cost p/week)
| A | None | 6 | 6 | N/A |
| B | None | 5 | 2 | $500 |
| C | A | 3 | 2 | $1000 |
| D | A,B | 4 | 2 | $2000 |
| E | C,D | 5 | 2 | $1250 |
| F | D | 4 | 2 | $1000 |
*Shortest possible time for the task
-
Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task
-
List the tasks on the critical path
-
What is the expected project duration in weeks?
-
What is the slack for each activity?
A: B: C: D: E: F:
-
The project needs to be crashed by 2 weeks. What are the activities crashed to achieve the 2 week crash at lowest cost? List the new duration of each task and any associated crash costs
Activity Duration Crash Cost
A
B
C
D
E
F
-
Draw the NEW project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task
-
List the tasks on the critical path