Question: Consider a sequential production process with 3 stages. The processing time (min per unit) and number of employees at each state are as follows; Processing
Consider a sequential production process with 3 stages. The processing time (min per unit) and number of employees at each state are as follows;
Processing time. Number of workers
Stage 1: 8 min/unit. 1 worker
Stage 2: 4 min/unit. 1 worker
Stage 3. 10 min/unit. 2 workers
If Demand rate is 10 units per hour, what is the flow rate:
7.5
10
15
60
87
If the demand rate is 10 units per hour, what is the utilization of stage 2:
50%
20.0%
10.7%
40.0%
16.7%
If the demand rate is 10 units per hour, what is the cycle time in minutues
8
2
4
6
10