Question: Consider a serial sequence of 3 tasks - Station 1, Station 2 and Station 3. The time taken at each workstation to process a unit

Consider a serial sequence of 3 tasks - Station 1, Station 2 and Station 3. The time taken at each workstation to process a unit of the product is given in the figure below.

station 1= 4mis/unit

station 2= 6 mins/unit

station 3 = 5 mins/unit

Which of the following statements is FALSE?

A. Station 2 is the bottleneck

B. The capacity of the process is 10 units per hour

C. Station 3 utilization is 83.33%

D. The capacity at Station 1 is 16 units per hour.