Question: Consider a shirt - stitching process. The raw material for one shirt arrives as two sheets. One sheet ( the front ) goes to worker
Consider a shirtstitching process. The raw material for one shirt arrives as two sheets. One sheet the front goes to worker A who takes minutes to process it The other sheet the back goes to worker. B who takes minutes to process it So A and B are done simultaneously, not sequentially: Once both front and back are ready, they go to worker who stitches them together minutes then to D Ironing minutes and to packing minutes All steps A B C D and E are necessary to create each finished unit. Each step employs a single worker. The capacity of this process in an hour day is:
units
units
units
units