Question: Consider a single activity process with 1 worker. The activity time is 4 minutes per unit. The defect rate is 40% and the defective items
Consider a single activity process with 1 worker. The activity time is 4 minutes per unit. The defect rate is 40% and the defective items are routed to a sperate rework station with 2 workers. The rework time is 16 minutes per unit. The process capacity is within
Question 1 options:
|
|
Below 8 units per hour
|
|
|
8.1 - 16 units per hour
|
|
|
16.1 20 units per hour
|
|
|
20.1 24 units per hour
|
|
|
Above 24.1 units per hour
|