Question: Consider a single machine workstation processing parts in batches. The batch size is 20 parts, and a setup time of 1 hour is required before
Consider a single machine workstation processing parts in batches. The batch size is 20 parts, and a setup time of 1 hour is required before the start of processing of the batch. The process time to process the complete batch is 10 min. What is the effective process time per part in seconds?
a) 210
b) None of the above
c) 30
d) 600
e) 180