Question: Consider a small project that involves the following activities. Task Predecessors Optimistic a Most Likely m Pessimistic b A none 2 5 8 B A
Consider a small project that involves the following activities.
| Task | Predecessors | Optimistic a | Most Likely m | Pessimistic b |
| A | none | 2 | 5 | 8 |
| B | A | 1 | 2 | 9 |
| C | A | 0.25 | 0.5 | 3.75 |
| D | B | 1 | 1 | 7 |
| E | B and C | 1 | 2 | 9 |
| F | D and E | 1 | 3 | 11 |
Required:
- Determine the expected time and variance for each activity.
- Develop a network for this problem.
- Find ES, EF, LS, LF and the slack for each activity.
- Determine the critical path and the total project completion time.
- Determine the variance and the standard deviation of the critical path.