Question: Consider a three sequentially stepped process named as Process A , Process B , and Process C . Input comes into Process A . Output
Consider a three sequentially stepped process named as Process A Process B and Process C Input comes into Process A Output from A goes into Process B Output from goes into Process Output of is the final output. Suppose the cycle time of each is: A minutes per unit, minutes per unit and minute per unit. Process A receives input at the rate of per hour. Which processes will be experiencing starving?
Process A and Process B
Process B and Process C
Procams A
Process B
Process C