Question: Consider a three sequentially stepped process named as Process A, Process B and Process C. Input comes into Process A. Output form A goes into

Consider a three sequentially stepped process named as Process A, Process B and Process C. Input comes into Process A. Output form A goes into Process B. Output from B goes into Process C. Output of C is the final output. Suppose that it takes 2 minutes per unit in Process A, 2 minutes per unit in Process B and 1 minute per unit in Process C. What will be maximum steady state output from this systems?