Question: Consider a three - step manufacturing process with one worker at each station operating in a batch size of 4 products / batch: Assumption: Each

Consider a three-step manufacturing process with one worker at each station operating in a batch size of 4 products/batch:
Assumption:
Each day starts with an empty line/process
Setup once only for a day at the beginning of the shift
WIP is transferred to the next step by each piece instead of batch
Step 1 Step 2 Step 3
Set up Time 40 mins 50 mins 55 mins
Run Time (per unit)12 mins 10 mins 8 mins
Questions:
Identify the bottleneck
What is the daily process capacity?
What is the process capacity if one worker is assigned to Step 1+2 and another one is to Step 3?
Question 1 Answer
a.
Q1: Bottleneck is Step 3
Q2: Process Capacity is 52.25
Q3: Process Capacity is 42.8
b.
Q1: Bottleneck is Step 2
Q2: Process Capacity is 42,8
Q3: Process Capacity is 52.25
c.
Q1: Bottleneck is Step 1
Q2: Process Capacity is 36.6
Q3: Process Capacity is 17.73

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!