Question: Q 4) Consider a three-step manufacturing process with one worker at each station operating in a batch size of 4 products/batch: Step 1 Step 2
Q 4) Consider a three-step manufacturing process with one worker at each station operating in a batch size of 4 products/batch:
|
| Step 1 | Step 2 | Step 3 |
| Set up Time | 40 mins | 50 mins | 55 mins |
| Process Time | 12 mins | 10 mins | 8 mins |
(a) Identify the bottleneck.
(b) Compute utilization for each station.
(c) What is the daily process capacity?
(d) Did you notice any work balancing issue?