Question: Q 4) Consider a three-step manufacturing process with one worker at each station operating in a batch size of 4 products/batch: Step 1 Step 2

Q 4) Consider a three-step manufacturing process with one worker at each station operating in a batch size of 4 products/batch:

Step 1

Step 2

Step 3

Set up Time

40 mins

50 mins

55 mins

Process Time

12 mins

10 mins

8 mins

(a) Identify the bottleneck.

(b) Compute utilization for each station.

(c) What is the daily process capacity?

(d) Did you notice any work balancing issue?