Question: Consider a three - workstation flowline. The workstations each have an infinite buffer and contain 1 , 4 , and 2 machines respectively. The process

Consider a three-workstation flowline. The workstations each have an infinite buffer
and contain 1,4, and 2 machines respectively. The process time of the machines in
workstation 1,2 and 3 is 0.15,0.8, and 0.35 hours respectively.
(i) Calculate the maximum throughput of the line.
(ii) Determine the flow time of a lot for release rates under the maximum throughput.
(iii) Determine the mean WIP-level in the line for the maximum throughput.