Question: Consider a three-stage process with the stages named as Process A, Process B and Process C. Input comes into Process A. Output from Process A

Consider a three-stage process with the stages named as Process A, Process B and Process C. Input comes into Process A. Output from Process A goes into Process B. Output from Process B goes into Process C. Output of C is the final output. Suppose that it takes 2 minutes per unit in Process A, 3 minutes per unit in Process B, and 1 minute per unit in Process C. What would be the decision tree for this question as well as the working for which decision should be made