Question: Consider a three-stage process with the stages named A, B, and C. Input comes into A. Output from A goes into B, and output from
Consider a three-stage process with the stages named A, B, and C. Input comes into A. Output from A goes into B, and output from B goes into C. Output of C is the final output. Suppose that it takes 2 minutes per unit in A, 3 minutes per unit in B, and 1 minute per unit in C. Which stage is the bottleneck?
Question 2 options:
|
|
Stage A
|
|
|
Stage B
|
|
|
Stage C
|
|
|
The process does not have a bottleneck
|