Question: Consider a workstation that can process 600 units per hour. It takes 1.5 hours to receive an order from the previous station. The container size

Consider a workstation that can process 600 units
Consider a workstation that can process 600 units per hour. It takes 1.5 hours to receive an order from the previous station. The container size is 90 units. The factory sets safety stock at thirty percent of demand during lead time. How many kanbans are needed for the workstation? O 10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!