Question: Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 10, 28, 56. Find the mean value of the activity time. (Please
Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 10, 28, 56. Find the mean value of the activity time.
(Please provide answer accurate to two decimal places)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts