Question: Consider an activity with these estimates for optimistic, most likely, and pessimistic times: 5, 8, 20 (weeks). Find the mean value of the activity time.
Consider an activity with these estimates for optimistic, most likely, and pessimistic times: 5, 8, 20 (weeks). Find the mean value of the activity time. (include one decimal place)