Question: Consider an assembly line with 3 sequential operations A, B, and C with processing rates 10, 40, and 30parts per hour, respectively. What is the
Consider an assembly line with 3 sequential operations A, B, and C with processing rates 10, 40, and 30parts per hour, respectively. What is the cycle time of the process on a day when Chris is absent, and Abe is the only worker