Question: Consider an assembly line with 3 sequential operations A, B, and C with processing times per part of 10, 20, and 40 minutes, respectively. Each

Consider an assembly line with 3 sequential operations A, B, and C with processing times per part of 10, 20, and 40 minutes, respectively. Each operation has a dedicated worker. The steady state process capacity in parts per 8-hour day is