Question: Consider an IT development project network given below The systems analyst has made estimates of the optimistic, most probable, and pessimistic times ( in days

Consider an IT development project network given below
The systems analyst has made estimates of the optimistic, most probable, and pessimistic times (in days) for these activities as follows:
Activity Optimistic Most Probable Pessimistic
\table[[A,5,6,7],[B,5,12,13],[C,6,8,10],[D,4,10,10],[E,5,6,13],[F,7,7,10],[G,4,7,10]]
Determine the expected project completion time and the variance:
 Consider an IT development project network given below The systems analyst