Question: Consider an IT development project network given below The systems analyst has made estimates of the optimistic, most probable, and pessimistic times ( in days

Consider an IT development project network given below
The systems analyst has made estimates of the optimistic, most probable, and pessimistic times (in days) for these activities as follows:
Activity Optimistic Most Probable Pessimistic
\table[[A,5,6,7],[B,5,12,13],[C,6,8,10],[D,4,10,10],[E,5,6,13],[F,7,7,10],[G,4,7,10]]
How much slack time, if any, is there for activity C?
Determine the expected project completion time and the variance:
Find the probability that the project will he completed in 30 days or less:
 Consider an IT development project network given below The systems analyst

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!