Question: Consider an item whose leadtime is 1 week, lot sizing method is FOQ(50), safety stock requirement is 10 units, and available on-hand inventory is 30

Consider an item whose leadtime is 1 week, lot sizing method is FOQ(50), safety stock requirement is 10 units, and available on-hand inventory is 30 units. Fill out the following MRP table and answer the questions.

Week

1

2

3

4

5

6

LT=1

FOQ(50)

SS=10

OH=30

GR

100

90

SR

50

PAB

PR

POR

What is the projected available balance of the item at the end of week 2? ---units

What should be the planned receipt of the item in week 3? --- units

What should be the planned order release of the item in week 4? ---- units

What is the projected available balance of the item at the end of week 6? --- units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!