Question: (Question 7-10) Consider an item whose leadtime is 1 week, lot sizing method is FOQ(5), safety stock requirement is 10 units, and available on-hand inventory
(Question 7-10) Consider an item whose leadtime is 1 week, lot sizing method is FOQ(5), safety stock requirement is 10 units, and available on-hand inventory is 30 units. Fill out the following MRP table and answer the questions.
|
| Week | 1 | 2 | 3 | 4 | 5 | 6 |
| LT=1 FOQ(50) SS=10 OH=30 | GR |
|
| 100 |
| 60 |
|
| SR |
| 60 |
|
|
|
| |
| PAB |
|
|
|
|
|
| |
| PR |
|
|
|
|
|
| |
| POR |
|
|
|
|
|
|
7. What is the projected available balance of the item at the end of week 2?
Group of answer choices
0
20
60
80
100
8.
What should be the planned receipt of the item in week 3?
Group of answer choices
0
20
50
100
180
9.
What should be the planned order release of the item in week 4?
Group of answer choices
0
20
50
90
100
10.
What is the projected available balance of the item at the end of week 6?
Group of answer choices
0
20
30
80
100