Question: Consider an operation with an average processing time of 4 minutes per unit with a CV 2 = 0.5. After returning from a lean mfg.

Consider an operation with an average processing time of 4 minutes per unit with a CV2 = 0.5. After returning from a lean mfg. conference, one of your associates suggests reconfiguring the system into a 5 station work cell. Each station would perform part of the overall task. The processing time at each station is 0.8 minutes with a CV2 = 0.5. Is this reconfiguration to a work cell an improvement from a variability perspective?