Question: Consider following projects with 7 activities: Activity Duration ( days ) Immediate Predecessor A 4 - - B 3 A C 5 A D 2
Consider following projects with activities:
Activity Duration days Immediate Predecessor
A
B A
C A
D A
E BC
F CD
G EF
Match the activities with the Early Start Time, Early Finish Time, Late Start Time, Late Finish Time, Total Slack combinations if the project is scheduled to be completed in the earliest time.