Question: Consider P 3 | prmp | Cj with the additional constraint that the completion of job j has to be less than or equal to

Consider P3| prmp |
Cj with the additional constraint that the completion
of job j has to be less than or equal to a given fixed deadline dj. Preemptions
may occur only at integer times 1,2,3,...
jobs 1234567891011
pj 23358889121416
dj \infty \infty \infty \infty \infty \infty 1112132829
Find the optimal schedule and compute the total completion time.