Question: Consider Table 6.3 from your text book, below Table 6-3. Activity Network diagram data for a large project Initial Node Final Node Estimated Duration 1

Consider Table 6.3 from your text book, below

Consider Table 6.3 from your text book, below Table 6-3. Activity Network diagram data for a large project Initial Node Final Node Estimated Duration 1 2 10 1 3 12 1 4 2 3 2 5 3 4 4 5 4 6 5 6 5 8 6 7 8 7 8 10 1. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time ABCDEF I _ XL G H I J K 01 00 +00 6.0 + 00 60 2 4 8 4 8 12