Consider the activities, durations, and predecessor relationships in the following network. Draw the network and answer the
No answer yet for this question.
Ask a Tutor
Question:
Consider the activities, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow.
Activity Description | Immediate Predecessor(s) | Optimistic (Weeks) | Most Likely (Weeks) | Pessimistic (Weeks) |
A | --- | 4 | 7 | 10 |
B | A | 2 | 8 | 20 |
C | A | 8 | 12 | 16 |
D | B | 1 | 2 | 3 |
E | D, C | 6 | 8 | 22 |
F | C | 2 | 3 | 4 |
G | F | 2 | 2 | 2 |
H | F | 6 | 8 | 10 |
I | E, G, H | 4 | 8 | 12 |
J | I | 1 | 2 | 3 |
a) Draw the precedence diagram. (5 points)
b) What is the critical path? (5 points)
c) What is the probability of completion of the project after week 42?