Question: Consider the AON graph of a project shown below. The activity times are 3 , 3 , 1 , 5 , 5 , 1 ,

Consider the AON graph of a project shown below.
The activity times are 3,3,1,5,5,1,2, and 2 days for activities A1 through A8, respectively.
If necessary, redraw the diagram, calculate forward pass and backward pass, calculate slack, find the critical path and find out the earliest completion time of the project?