Question: Consider the appended project information. What is the critical path? A=2 weeks B=12 weeks, C=3 weeks, D=14 weeks, E=17 weeks, F=2 weeks, G=2 weeks, H=1
Consider the appended project information. What is the critical path? A=2 weeks B=12 weeks, C=3 weeks, D=14 weeks, E=17 weeks, F=2 weeks, G=2 weeks, H=1 week. Both activity C and D are parallel processes.
options:
|
| ABCEGH |
|
| ABCEFH |
|
| ABDEFH |
|
| ABDEGH |