Question: Consider the assembly process as described in the below table. The production rate is required to be 80 products per hour and the plant is
Consider the assembly process as described in the below table. The production rate is required to be 80 products per hour and the plant is operating 80 minutes per hour with no down time, breaks, and other stoppages to represent. Calculate Cycle time
| Task | Process Time(seconds) | Immediate Predecessor |
| A | 35 | - |
| B | 20 | A |
| C | 15 | A |
| D | 5 | C |
| E | 5 | D |
| F | 12 | D |
| G | 10 | D |
| H | 5 | E,F,G |
| I | 5 | H |
Select one:
a. 1 hr/unit
b. 0.75 mins/unit
c. 1 min/unit
d. 0.75 hrs/unit