Question: Consider the below activity table for a project: Activity Immediate Predecessor Time (Days) A -- 8 B -- 3 C A 7 D A, B
Consider the below activity table for a project:
| Activity | Immediate Predecessor | Time (Days) |
|---|---|---|
| A | -- | 8 |
| B | -- | 3 |
| C | A | 7 |
| D | A, B | 3 |
| E | C, D | 4 |
| F | C, D | 6 |
Which of the following show the project duration?
- 31
- 17
- 19
- 21
- 15
- None of the above (What is your answer?)
- Reconsider the Q3, which of the following shows the latest start time of activity B?
- 0
- 3
- 8
- 12
- 9
- None of the above (What is your answer?)
- Reconsider the Q3, which of the following shows the latest finish time of activity D?
- 15
- 17
- 11
- 21
- 13
- None of the above (What is your answer?)
- Reconsider the Q3, which of the following shows the earliest start time of activity F?
- 11
- 15
- 17
- 8
- 21
- None of the above (What is your answer?)
- Reconsider the Q3, what is the minimum number of non-critical activities that have to be delayed for the project to get delayed?
- 1
- 2
- 3
- 4
- 5
- None of the above (What is your answer?)
- Reconsider the Q3, what is the maximum number of activities that can be delayed for the project not to get delayed?
- 1
- 2
- 3
- 4
- 5
- None of the above (What is your answer?)
- Reconsider the Q3, what is the maximum number of activities that can be delayed for the project not to have additional critical activities?
- 1
- 2
- 3
- 4
- 5
- None of the above (What is your answer?)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock