Question: Consider the below activity table for a project for the questions 13-20. Activity Immediate Predecessor Duration Resource Start --- 0 --- A --- 4 Yellow
Consider the below activity table for a project for the questions 13-20.
| Activity | Immediate Predecessor | Duration | Resource |
| Start | --- | 0 | --- |
| A | --- | 4 | Yellow |
| B | A | 6 | Gray |
| C | B, E | 2 | Orange |
| D | --- | 6 | Gray |
| E | D | 4 | Blue |
| F | C | 4 | Green |
| G | F | 4 | Yellow |
| Finish |
| 0 | --- |
- Which of the following is a possible Critical Chain of the project?
- A B C F G
- A B E C F G
- D E C F G
- A B D E C F G
- A B D C F G
- None of the above
- Which of the following is a possible project duration (including project buffer) after applying the Critical Chain?
- 24
- 15
- 11
- 17
- 18
- None of the above
- Which of the following shows the buffers of the project after applying the critical chain assuming D B C F G is the Critical Chain of the project?
- 2 Feeding Buffers with 1 day each and 1 Project Buffer with 6 days
- 2 Feeding Buffers with 2 days each and 1 Project Buffer with 6 days
- 3 Feeding Buffers with 1 day each and 1 Project Buffer with 5 days
- 1 Feeding Buffer with 1 day each and 1 Project Buffer with 5 days
- 3 Feeding Buffers with 1 day each and 1 Project Buffer with 6 days
- None of the above (what is your answer?)
- Which of the following shows the latest finish time of activity E in the final schedule after applying the critical chain?
- 6 or 10
- 7 or 10
- 6 or 11
- 7 or 11
- 6 or 9
- None of the above (what is your answer?)
- Which of the following shows the latest finish time of activity F in the final schedule after applying the critical chain?
- 10 or 14
- 9 or 14
- 9 or 13
- 10 or 13
- 8 or 12
- None of the above (what is your answer?)
- Which of the following shows the latest start time of activity C in the final schedule after applying the critical chain?
- 6 or 10
- 7 or 10
- 6 or 11
- 7 or 11
- 6 or 9
- None of the above (what is your answer?)
- Which of the following shows the latest start time of activity G in the final schedule after applying the critical chain?
- 9 or 14
- 10 or 14
- 9 or 15
- 8 or 13
- 10 or 13
- None of the above (what is your answer?)
- Which of the following is a possible non-critical activity in the final schedule after applying the critical chain?
- A
- B
- C
- D
- F
- None of the above