Question: Consider the below activity table for a project for the questions 13-20. Activity Immediate Predecessor Duration Resource Start --- 0 --- A --- 4 Yellow

Consider the below activity table for a project for the questions 13-20.

Activity

Immediate Predecessor

Duration

Resource

Start

---

0

---

A

---

4

Yellow

B

A

6

Gray

C

B, E

2

Orange

D

---

6

Gray

E

D

4

Blue

F

C

4

Green

G

F

4

Yellow

Finish

0

---

  1. Which of the following is a possible Critical Chain of the project?
  1. A B C F G
  2. A B E C F G
  3. D E C F G
  4. A B D E C F G
  5. A B D C F G
  6. None of the above

  1. Which of the following is a possible project duration (including project buffer) after applying the Critical Chain?
  1. 24
  2. 15
  3. 11
  4. 17
  5. 18
  6. None of the above

  1. Which of the following shows the buffers of the project after applying the critical chain assuming D B C F G is the Critical Chain of the project?
  1. 2 Feeding Buffers with 1 day each and 1 Project Buffer with 6 days
  2. 2 Feeding Buffers with 2 days each and 1 Project Buffer with 6 days
  3. 3 Feeding Buffers with 1 day each and 1 Project Buffer with 5 days
  4. 1 Feeding Buffer with 1 day each and 1 Project Buffer with 5 days
  5. 3 Feeding Buffers with 1 day each and 1 Project Buffer with 6 days
  6. None of the above (what is your answer?)
  1. Which of the following shows the latest finish time of activity E in the final schedule after applying the critical chain?
  1. 6 or 10
  2. 7 or 10
  3. 6 or 11
  4. 7 or 11
  5. 6 or 9
  6. None of the above (what is your answer?)

  1. Which of the following shows the latest finish time of activity F in the final schedule after applying the critical chain?
  1. 10 or 14
  2. 9 or 14
  3. 9 or 13
  4. 10 or 13
  5. 8 or 12
  6. None of the above (what is your answer?)

  1. Which of the following shows the latest start time of activity C in the final schedule after applying the critical chain?
  1. 6 or 10
  2. 7 or 10
  3. 6 or 11
  4. 7 or 11
  5. 6 or 9
  6. None of the above (what is your answer?)

  1. Which of the following shows the latest start time of activity G in the final schedule after applying the critical chain?
  1. 9 or 14
  2. 10 or 14
  3. 9 or 15
  4. 8 or 13
  5. 10 or 13
  6. None of the above (what is your answer?)
  1. Which of the following is a possible non-critical activity in the final schedule after applying the critical chain?
  1. A
  2. B
  3. C
  4. D
  5. F
  6. None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!