Question: Consider the below project information for the questions 6-12. Normal Cost Crash Cost ($) Activity | Immediate Predecessor Normal Duration (days) Crash Duration (days) 40

Consider the below project information for the

Consider the below project information for the questions 6-12. Normal Cost Crash Cost ($) Activity | Immediate Predecessor Normal Duration (days) Crash Duration (days) 40 2 5 150 200 250 50 525 290 250 180 AC , B D E, F 1 7 F 1080 50 6 60 H 3 Q6. Which of the following shows the maximum number of activities we can crash to reduce the duration the project at most 1 day? A) 1 B) 2 C) 3 D) 4 F) None of the above (what is your answer?)