Question: Consider the below project network diagram with lags. Answer the following questions regarding Early Start, Early Finish, Late Start, Late Finish, and Slack values. Question
Consider the below project network diagram with lags.
Answer the following questions regarding Early Start, Early Finish, Late Start, Late Finish, and Slack values.
Question 9 (7 points)
What is the value of "W"?
a. 1
b.4
c.3
d.0
e.5
what is the value of A
a. 10
b.8
c.11
d.7
e.9
what is the value of b
a.19
b.14
c.8
d.11
e.11
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
