Consider the dependency matrix and the activity durations provided below.
Downstream Activity | Upstream Activity | ||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | ||
1 | |||||||||||
2 | X | ||||||||||
3 | X | ||||||||||
4 | X | ||||||||||
5 | X | ||||||||||
6 | X | ||||||||||
7 | X | ||||||||||
8 | X | ||||||||||
9 | X | X | |||||||||
10 | X | X | |||||||||
Activity | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Time | 9 | 8 | 12 | 9 | 1 | 16 | 8 | 11 | 10 | 2 |