Question: Consider the example in Section 8 . 8 . The arrival rate of jobs is 1 3 . 5 jobs per hour ( with c

Consider the example in Section 8.8. The arrival rate of jobs is 13.5 jobs per hour (with
c2
a =1) to a workstation consisting of five machines. Each machine nominally takes 0.3
hour per job with a natural CV of 1
2(that is, c2
0=0.25). The mean time to failure for any
machine is 36 hours, and repair times are exponential with a mean time to repair of
4 hours.
(a) Show that the SCV of effective process times is 2.65.
(b) What is the utilization of a single machine when it is allocated one-fifth of the demand
(that is,2.7 jobs per hour) assuming ca is still equal to 1?
(c) What is the utilization of the station with an arrival rate of 13.5 jobs per hour?
(d) Compute the mean cycle time at a single machine when allocated one-fifth of the
demand.
(e) Compute the mean cycle time at the station serving 13.5 jobs per hour.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!